2024 Surface Seal Project
At the Lafayette City Council meeting of May 13, 2024, a construction contract for the 2024 Surface Seal Project, in the amount of $2,481,000, was awarded to VSS International, West Sacramento, CA. The project included work on the following streets:
- Acalanes Road -Hidden Valley road to El Nido Ranch Road
- Fallen Leaf Court - Silver Dell Road to End
- Golden Gate Way - First Street to Mount Diablo Boulevard
- Goyak Drive -Springhill Road to End
- Hermosa Court - Camino Colorados to End
- Hillcrest Drive - Laurel Drive to End
- Lucas Circle - North intersection with Lucas Drive to south intersection with Lucas Drive
- Mount Diablo Boulevard - El Nido Ranch Road to Dolores Drive
- Mountain View Drive - Mount Diablo Boulevard to Brook Street
- Oak Court - Sweet Drive to end of public segment of Oak Court
- Pleasant Hill Road - Mount Diablo Boulevard to Olympic Boulevard
- Quandt Road - Del Arroyo Court to Woodborough Road
- Saint Mary's Road - Rohrer Drive to southern City Limit
- Sibert Court - Tanglewood Drive to End
- Tanglewood Drive - Moraga Road to Sibert Court
- Vacation Drive - Stanley Boulevard to End
Construction
Construction was essentially completed in September 2024. Click HERE for final Friday Weekly Update.
Microsurfacing (Slurry) Schedule Resident Notification Letter, July 2024
Resident Notification Letter, 6-7-24
Bid Opening Results, 5/1/24:
Pre-Bid Documents