2024 Road Paving and Surface Seal Projects

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Spring/Summer 2024 Roadwork Projects:

Surface Seal Project (including Roundabout Improvements)

Road Construction Project Began:  June, 2024
Completion:  Mid-September, 2024

Streets Being Resealed

  • Acalanes Road - Hidden Valley road to El Nido Ranch Road
  • Fallen Leaf Court - Silver Dell Road to End 
  • Golden Gate Way - First Street to Mount Diablo Boulevard
  • Goyak Drive -Springhill Road to End
  • Hermosa Court - Camino Colorados to End
  • Hillcrest Drive - Laurel Drive to End
  • Lucas Circle - All
  • Mount Diablo Boulevard - El Nido Ranch Rd to Dolores Dr
  • Mountain View Drive - Mount Diablo Blvd to Brook St
  • Oak Court - Sweet Dr to end of public segment of Oak Ct
  • Pleasant Hill Road - Mount Diablo Blvd to Olympic Blvd
  • Quandt Road - Del Arroyo Court to Woodborough Road
  • Saint Mary's Road - Rohrer Drive to southern City Limit
  • Sibert Court - Tanglewood Drive to End
  • Tanglewood Drive - Moraga Road to Sibert Court
  • Vacation Drive - Stanley Boulevard to End

Construction Schedule 

During construction, check back HERE for the Friday Weekly Update

Construction hours: 8 am to 5 pm weekdays.  No planned roadwork on weekends or City holidays.

Project Details

Read more about the 2024 Surface Seal Project

Contacts

Contractor: VSS International

City: Tim Clark, Associate Engineer Send an email or call 925‐299‐3245.

Road Paving Project

Road Construction Project Began:  June, 2024
Completion:  September, 2024

Streets Being Repaved & Raised Crosswalks

  • Acalanes Road - Black Forest Court to City Limits
  • Pine Lane - El Nido Ranch Road to the End
  • Angelo Street - Reliez Valley Road to the End
  • Taylor Boulevard - Pleasant Hill Road to City Limits
  • Pleasant Hill Road Southbound lane from Springhill Road to Greenvalley Drive
  • Pleasant Hill Road Northbound lane from Quandt Road to 150' north of Reliez Valley Road (City limits)
  • Raised Crosswalk on Springhill Road
  • Raised Crosswalk on Stanley Blvd

Construction Schedule 

Construction is essentially completed. Check HERE to read the final Friday Weekly Update

Project Details

Read more about the 2024 Road Paving Project

Contacts

Contractor: JV Lucas Paving, Inc.,  Antony Perez, Project Manager, 925-348-6648

City:  Ana Bernardes, Senior Engineer  Send an email or call 925‐299‐3209.